Project

General

Profile

Actions

Task #1224

closed

Swiss hosting setup

Added by Florian Effenberger over 9 years ago. Updated over 8 years ago.

Status:
Closed
Priority:
Normal
Category:
-
Target version:
Team - Q1/2016
Start date:
Due date:
% Done:

80%

Tags:

Description

We want to make use of the Swiss hosting offer. Machines to be shipped there:


Related issues

Related to Infrastructure - Task #1317: SQL replicationNewNorbert Thiebaud

Actions
Actions #1

Updated by Florian Effenberger over 9 years ago

Waiting for answer by our Swiss friends - big question is bandwith

Actions #2

Updated by Florian Effenberger over 9 years ago

We also have 0,5 TB at manitu that we can make use of - it's onsite, but adds further redundancy

Actions #3

Updated by Florian Effenberger over 9 years ago

  • Due date deleted (2015-05-17)

poke Nicholas again ASAP and if nothing timely from him, then go for a dedicated box at Hetzner for offsite backup

Actions #4

Updated by Alexander Werner over 9 years ago

  • Status changed from In Progress to Feedback

Waiting for Feedback from Nicolas about Housing a server.

Actions #5

Updated by Florian Effenberger over 9 years ago

Swiss option seems to work; let's discuss about something in our office as well, having something we can "touch" makes sense in parallel. Let's talk next week.

Actions #6

Updated by Alexander Werner over 9 years ago

Ad interim: Additional Backup Server at Hetzner ordered.

Actions #8

Updated by Alexander Werner over 9 years ago

  • Priority changed from Normal to Immediate
Actions #9

Updated by Alexander Werner over 9 years ago

  • Status changed from Feedback to In Progress

Setting up intermediate Backup at Hetzner

Actions #10

Updated by Alexander Werner over 9 years ago

  • Priority changed from Immediate to Urgent

Intermediate backup at Hetzner was setup. Lowering priority for the swiss backup.

Actions #11

Updated by Florian Effenberger over 9 years ago

Actions #12

Updated by Alexander Werner over 9 years ago

768GB backed up by intermediate server and counting...

Actions #13

Updated by Florian Effenberger over 9 years ago

  • Description updated (diff)
Actions #14

Updated by Florian Effenberger over 9 years ago

  • Subject changed from external backup solution to external backup solution and hosting
  • Description updated (diff)
Actions #15

Updated by Florian Effenberger over 9 years ago

Call with Krenn on Monday

Actions #16

Updated by Florian Effenberger over 9 years ago

  • Description updated (diff)
Actions #17

Updated by Florian Effenberger about 9 years ago

  • Target version set to Q4/2015
Actions #18

Updated by Florian Effenberger about 9 years ago

  • Subject changed from external backup solution and hosting to Swiss hosting setup
  • Description updated (diff)
  • Priority changed from Urgent to Normal
  • % Done changed from 0 to 30
Actions #19

Updated by Florian Effenberger about 9 years ago

There's a proposal to have some LibO evening event alongside to foster the local community
Local setup is possible during the week or Friday to Saturday
Keep in mind machine needs ordering and customs need dealing with, so plan in time!

Proposals from the Swiss folks:
  • CW 44
  • CW 46
  • CW 47
  • CW 50
Actions #20

Updated by Florian Effenberger almost 9 years ago

  • Target version changed from Q4/2015 to Q1/2016

Customs and shipment handling took too much time, so postponing to Q1. Hardware ordered and will be stored/shipped to Krenn, then in January 2016 planning setup date in Switzerland. In the meantime, customs EORI number arrived and logistics company confirmed they can do the handling.

Actions #21

Updated by Alexander Werner almost 9 years ago

IP Sockets will only be shipped after 29 January, postponing after FOSDEM

Actions #22

Updated by Alexander Werner over 8 years ago

  • % Done changed from 30 to 80

All Hardware is now at Thomas Krenn, only some more Paperwork required.

Actions #23

Updated by Alexander Werner over 8 years ago

  • Status changed from In Progress to Closed
Actions

Also available in: Atom PDF