Actions
Task #1841
closedSetup of Intranet Hardware for Manitu Rack
Start date:
Due date:
2016-03-24
% Done:
30%
Tags:
URL:
Description
The ordered servers from TK, the 10G switch, the 1G switch need to be setup and configured.
Related issues
Updated by Alexander Werner almost 9 years ago
Dicke Berta is configured except final network configuration.
Updated by Alexander Werner almost 9 years ago
- Blocks Task #1835: migration to own rack added
Updated by Alexander Werner almost 9 years ago
- Due date set to 2016-03-11
- % Done changed from 0 to 30
Updated by Alexander Werner over 8 years ago
- Due date changed from 2016-03-11 to 2016-03-24
Delayed due to Bern and CeBit.
Updated by Florian Effenberger over 8 years ago
- Target version changed from Q1/2016 to Q2/2016
Feedback from manitu, the migration can start during the next days
We need to plan in some advance notice and downtime, but I expect this to be carried out in April
Updated by Alexander Werner over 8 years ago
- Status changed from In Progress to Closed
Own hardware has been setup, follwing up in #1835
Actions