Task #814
closedInfrastructure Migration Plan
100%
Description
This is a Metaticket to Plan the Migration of the distinct VMs and Servers onto the new Platform.
Related issues
Updated by Alexander Werner about 10 years ago
The following are VMs that will be migrated:
ask
dev-downloads
gerrit
gerrit-test
jenkins
vm14
moztrap
As the images need to be copied into the new platform, there is a downtime of about 3 Minutes/GB image size, and the VMs need to be migrated one after another.
The preliminary plan is:
- 11 November, 0900UTC: Migration of dev-downloads
- 12 November, 0900UTC: Migration of gerrit-test
- 13 November, 0900UTC: Migration of vm14
- 14 November, 0900UTC: Migration of jenkins
- 17 November, 0900UTC: Migration of ask
- 28 November, 0900UTC: Migration of moztrap
- 29 November, 0900UTC: Migration of gerrit
Updated by Alexander Werner about 10 years ago
The following servers need to be migrated:
grisu
kermit
bilbo
floyd
gucky
The preliminary migration plan is:
- 26 November: floyd
- 1 December: kermit
- 2 December: grisu
- 3 December: bilbo
- 4 December: gucky
Updated by Alexander Werner about 10 years ago
- Precedes Feature #171: Create a Testwiki added
Updated by Alexander Werner about 10 years ago
Plan for cancellation of the servers is:
floyd - 1 December 2014
centos - 1 December 2014
bilbo - 5 December 2014
gru - 5 December 2014
kermit - 10 December 2014
grisu - 13 December 2014
gucky - 16 December 2014
Updated by Florian Effenberger almost 10 years ago
- Status changed from In Progress to Rejected
Rejecting this one, the topic needs to be revisited in light of the recent infra story