This is a Metaticket to Plan the Migration of the distinct VMs and Servers onto the new Platform.
The following are VMs that will be migrated:
ask
dev-downloads
gerrit
gerrit-test
jenkins
vm14
moztrap
As the images need to be copied into the new platform, there is a downtime of about 3 Minutes/GB image size, and the VMs need to be migrated one after another.
The preliminary plan is:
- 11 November, 0900UTC: Migration of dev-downloads
- 12 November, 0900UTC: Migration of gerrit-test
- 13 November, 0900UTC: Migration of vm14
- 14 November, 0900UTC: Migration of jenkins
- 17 November, 0900UTC: Migration of ask
- 28 November, 0900UTC: Migration of moztrap
- 29 November, 0900UTC: Migration of gerrit
The following servers need to be migrated:
grisu
kermit
bilbo
floyd
gucky
The preliminary migration plan is:
- 26 November: floyd
- 1 December: kermit
- 2 December: grisu
- 3 December: bilbo
- 4 December: gucky
Plan for cancellation of the servers is:
floyd - 1 December 2014
centos - 1 December 2014
bilbo - 5 December 2014
gru - 5 December 2014
kermit - 10 December 2014
grisu - 13 December 2014
gucky - 16 December 2014
- Status changed from In Progress to Rejected
Rejecting this one, the topic needs to be revisited in light of the recent infra story