Roadmap

Team - Q1/2020

locked

about 19 months late (2020-03-31)

First quarter of 2020: January, February and March

90%

32 issues   (29 closed3 open)

Team - Q2/2020

locked

about 16 months late (2020-06-30)

Second quarter of 2020: April, May and June

96%

31 issues   (30 closed1 open)

Team - Q3/2020

locked

about 13 months late (2020-09-30)

Third quarter of 2020: July, August and September

92%

26 issues   (24 closed2 open)

Team - Q4/2020

locked

about 10 months late (2020-12-31)

Fourth quarter of 2020: October, November and December

91%

19 issues   (17 closed2 open)

Team - Q1/2021

locked

about 7 months late (2021-03-31)

First quarter of 2021: January, February and March

100%

25 issues   (25 closed — 0 open)

Team - Q3/2021

open

23 days late (2021-09-30)

Third quarter of 2021: July, August and September

71%

26 issues   (17 closed9 open)

Team - Q1/2022

open

Due in about 5 months (2022-03-31)

First quarter of 2022: January, February and March

20%

5 issues   (1 closed4 open)

Team - Qlater

open

Unplanned quarters in the future

65%

60 issues   (39 closed21 open)

Team - Recurring

open

Recurring tasks

43%

73 issues   (32 closed41 open)