Waiting for answer by our Swiss friends - big question is bandwith
We also have 0,5 TB at manitu that we can make use of - it's onsite, but adds further redundancy
- Due date deleted (
2015-05-17)
poke Nicholas again ASAP and if nothing timely from him, then go for a dedicated box at Hetzner for offsite backup
- Status changed from In Progress to Feedback
Waiting for Feedback from Nicolas about Housing a server.
Swiss option seems to work; let's discuss about something in our office as well, having something we can "touch" makes sense in parallel. Let's talk next week.
Ad interim: Additional Backup Server at Hetzner ordered.
- Priority changed from Normal to Immediate
- Status changed from Feedback to In Progress
Setting up intermediate Backup at Hetzner
- Priority changed from Immediate to Urgent
Intermediate backup at Hetzner was setup. Lowering priority for the swiss backup.
768GB backed up by intermediate server and counting...
- Description updated (diff)
- Subject changed from external backup solution to external backup solution and hosting
- Description updated (diff)
Call with Krenn on Monday
- Description updated (diff)
- Target version set to Q4/2015
- Subject changed from external backup solution and hosting to Swiss hosting setup
- Description updated (diff)
- Priority changed from Urgent to Normal
- % Done changed from 0 to 30
There's a proposal to have some LibO evening event alongside to foster the local community
Local setup is possible during the week or Friday to Saturday
Keep in mind machine needs ordering and customs need dealing with, so plan in time!
Proposals from the Swiss folks:
- Target version changed from Q4/2015 to Q1/2016
Customs and shipment handling took too much time, so postponing to Q1. Hardware ordered and will be stored/shipped to Krenn, then in January 2016 planning setup date in Switzerland. In the meantime, customs EORI number arrived and logistics company confirmed they can do the handling.
IP Sockets will only be shipped after 29 January, postponing after FOSDEM
- % Done changed from 30 to 80
All Hardware is now at Thomas Krenn, only some more Paperwork required.
- Status changed from In Progress to Closed